On June 21-22, we finished sheathing gable ends, installed windows, framed back porch cover, roofers came and prepared roof, heating ducts were installed, and electrical boxes installed! On June 28, soffits were finished (under eves) and siding started on east side of garage and north side of house. On June 29, continued siding installation, facia installed on eves, and back porch was covered.
2 Comments
Leave a Reply. |
AuthorTres Rios Habitat for Humanity is a non-profit, Christian ministry that brings the community together to build quality, Archives
November 2021
|
Tres Rios Habitat for Humanity |
Farmington Habitat ReStore |